Nestle A7

St. Louis, Missouri

Concrete Strategies performed the foundations, flatwork, precast erection, decorative sidewalks and loading dock renovations on this 7-story steel frame building.

Concrete Strategies performed the foundations, flatwork, precast erection, decorative sidewalks and loading dock renovations on this 7-story steel frame building.

There were 5,000-cubic-yards of concrete used to erect the 154 architectural precast panels. Due to site constraints and limited access, all precast panels had to be erected from the one side of the building. Concrete Strategies used a 275 ton crane with a 120-foot main boom and 120-foot of luffing jib to reach a 130-foot radius to safely erect the precast panels over the top of the building.

Key Facts

Client name:  Nestle Purina

Services Provided

Structural Foundations
Slab on Grade
Elevated Slab on Deck
Architectural Flatwork
Architectural Facade
Helical Anchors for Bracing